Rooms 11 & 12 Progress Report

There’s been good progress on the new rooms at Chanters Lodge again this week, with the coarses above the ring beam added as well as the gables on either end. The electricians have begun their work for wiring, and the plumbing materials have been ordered and paid for, awaiting delivery.

We’ve decided on the roofing materials and these as well as the door and window frames will be ordered and paid for tomorrow. The next major decisions will concern tiling. Plastering will follow the completion of the roof, and fitting door and window frames.

Completion date? Can’t say, sorry!