Progress Rooms 11 & 12


Just a quick check for you on the progress on our two roomed extension at Chanters Lodge, Livingstone. As you can see the plastering is complete, so too are the concrete floors, and the ceiling is in the process of being (noisily) fitted. Hot water geyzers are due to be fitted this week, and work will start on the drainage at the back of the extension. The tiler should be able to start in (less than?) a week or so.

We seem to be just about on target to have the new rooms finished and ready to let by November 15th.